Height kept to 2.4m and the building set 2.1m off the boundary, so it sits inside permitted development. We check this before quoting — a garden room that needs retrospective consent is not a saving.
Base
Insulated raft on compacted MOT and a DPM, rather than fence-post feet. It costs more on week one and it is the reason the door still closes in year five.
Shell
140mm timber frame filled with mineral wool, breather membrane, 25mm battened cavity and western red cedar on stainless fixings. Warm roof build-up with 120mm PIR above the deck, EPDM single-ply covering and a concealed gutter to a water butt.
Power and fit-out
10mm SWA buried at 600mm from the house consumer unit to its own board in the room: six doubles, two data points, LED panels on a dimmer and a 1kW panel heater that holds the room at 20°C on about 40p a day.
Cost and timescale
Four weeks including two rained-off days. £14,500 covering groundworks, shell, roof, cladding, electrics, plastered internal finish and decoration. Bifolds were customer supplied.