The brief
One room instead of two, an island the family could actually sit at, and a kitchen that would still look right in fifteen years rather than fifteen months.
The knock-through
Structural calcs commissioned, building control notified, a 152x89 UB installed on padstones with temporary props both sides. Signed off before a single unit arrived — no kitchen goes in ahead of the beam certificate.
Services
Gas run capped and re-routed for the 900mm range, ten new sockets on two circuits, waste re-fallen to the new sink position and the boiler flow rebalanced after the pipework moved. All tested and certificated.
Fitting
Carcasses levelled off the highest floor point, scribed to a wall that was 18mm out over four metres, and the island trued to the ceiling line rather than the floor so the eye reads it as straight. Quartz templated on day nine and fitted on day fifteen.
Cost and timescale
Three weeks on site. £9,400 for labour, steel, structural work, electrics, plumbing, plastering and fitting. Units, quartz and appliances were supplied by the customer at about £11,000.