The brief
No lip, no tray, nothing to trip on, and it had to look like a bathroom rather than a hospital.
Getting the floor right
Joists notched within permitted limits and a sloped former let into the deck so the finished tile falls 1:60 to a 900mm linear drain against the wall. Levels checked with a laser at three stages — a wet room that ponds is a wet room built by eye.
Waterproofing
Liquid membrane over the entire floor and 2m up the shower walls, reinforcing tape at every junction and pipe collar, left to cure a full day and flood-tested before tiling. That test day is not optional, whatever the schedule says.
Finish and safety
R11 slip-rated 300x600 floor tile, matching wall tile laid brick-bond, brushed steel grab rails fixed into noggins (never into board), thermostatic valve capped at 41°C and a fold-down seat set at the height the customer actually uses.
Cost and timescale
Nine working days, £5,200 including the former, drain, tanking, tiles and rails. No VAT relief was claimed here, but ask us — some adaptations qualify for zero-rating.